Written Answers. - Garda Stations.

  280. Mr. Stagg asked the Minister for Finance, further to his response to Questions Nos. 335 and 501 of 8 November 2005 from the Minister for Justice, Equality and Law Reform, if arrangements will be made for the commencement of the public consultation process for the new Garda station at Leixlip; and if he will make a statement on the matter. [34161/05]

  Mr. Parlon: Changes have been requested by the Garda authorities to the sketch scheme for the proposed Leixlip Garda station. Discussions are taking place between OPW and the Garda authorities on these changes. On agreement, the Part 9 planning process will proceed. This should take approximately six weeks after final agreement on all design issues.