Dáil Éireann - Volume 7 - 06 May, 1924 CEISTEANNA—QUESTIONS. ORAL ANSWERS. - RECONSTRUCTION OF BALLYVOYLE RAILWAY BRIDGE. Captain REDMOND Captain REDMOND Captain REDMOND asked the Minister for Industry and Commerce if he can state to what extent the reconstruction of the Railway Bridge at Ballyvoyle, County Waterford, has progressed and when it is expected to be completed. Mr. McGILLIGAN Mr. McGILLIGAN Mr. McGILLIGAN: One of the four steel spans has been fixed in position, two others are assembled ready to fix in position, and the fourth will be ready by the 7th instant. The completion of the work has taken longer than expected, but it is anticipated that the bridge will be open for traffic by the end of this month. Dáil Éireann 7 CEISTEANNA—QUESTIONS. ORAL ANSWERS. RECONSTRUCTION OF BALLYVOYLE RAILWAY BRIDGE. Questions 19240506
| ||||||||||||||||||||||